1. How to Put Tile (Zig Zag) 
Tile Installation must be done in Zig-Zag to reduce 
number of stacks overlap in one place, with the goal of getting 
piles overlap very precise so as to prevent water from entering 
on tile connection (Overlap). 
Tile should be installed tightly and blend with battens. 
2. Screw Fitting Method 
At the time of installation screw on the tile, the installation of the first screw 
should start at the center position strap water (red circles) and should 
proceed with the installation screw on the mounting position above 
The first screw (blue circle), then proceed with the installation 
screw the others. Screw position should be parallel to the slope of the roof and 
are not allowed to drill from the top. 
Screw connection should not be installed close to the tile (overlap) 
or water line to prevent water entering through the screw hole.